Oklahoma City-North Canadian WWTP

SiteWorks installation team change and repaired Oklahoma City treatment plant’s fouled membranes

Project Information

Project Type: Municipal Wastewater Treatment Plant

Completion Date: Summer 2024

Treatment Objectives:
Diffusers: 43,244
EPDM Disc

Download a Printable Version

You may also be interested in:

Project Background & Challenges

This wastewater treatment plant leads to the North Canadian River outside of Oklahoma City, Oklahoma was facing issues of many fouled-out membranes. With broken sections of pipe in their aeration system, they knew they needed experts for the repairs to get their plant up and running again as soon as they could.

The EDI Solution

EDI’s aeration experts proposed a membrane change in addition to inspecting and repairing throughout the whole system. This helped them save on total costs instead of completely gutting and replacing their existing system with a new one. With the reliability of a good-as-new system, and good-as-new performance, the system is now back and running smoothly just as the client needed.

Upgraded System Performance

The plant has been satisfied with the results since the project’s completion, and the construction company had the following to say about working with us and our representatives Newman Regency Group:

“On behalf of Wynn Construction, we would like to thank you for your promptness, attentiveness, and professionalism throughout this project. All involved did a great job. It was a pleasure doing business with you. Looking forward to future projects.” – Kevin Lang, Vice President of Wynn Construction